Interconnection queue

Also known as: grid interconnection queue, generator interconnection queue, grid connection queue

An interconnection queue is the line of proposed power plants and battery projects waiting for permission to connect to the electricity grid.

Before connecting, each project must be studied to see whether the grid can handle it and what upgrades are needed. While it sounds like paperwork, the queue has become one of the biggest bottlenecks in the energy transition: far more capacity is waiting to connect than is actually running in many regions.

Interconnection queue, explained at three levels

At home

Imagine a busy highway on-ramp with a long line of cars waiting to merge. Each new power project is a car, and the grid operator has to check that the highway has room before letting it on. That waiting line is the interconnection queue.

At work

Developers must enter the queue before building a power project. Long waits and uncertain upgrade costs can make projects miss financing windows, raising costs or killing them entirely.

Real-world examples

At home

Marcus joined a community solar co-op in Nova Scotia. He was surprised to learn the project would take more than two years to start, mostly because it was waiting for the utility to finish connection studies.

At work

Nadia is a development manager at a renewable energy company. Her wind project in the US Midwest sat in the queue for four years, and the final study assigned it a costly substation upgrade. The team added a battery to reshape its output and reduce the required upgrade.

Common confusions

  • Everything in the queue will eventually be built. — Most queued capacity is withdrawn. Only a small share historically reaches operation.
  • The queue is mostly fossil fuel plants. — In North America, most queued capacity is solar, storage, and wind.
  • Queues are just bureaucratic delays. — Studies address real physical limits. The bottleneck is often transmission capacity, not paperwork alone.

For analysts

For any energy project timeline, I'd ask where it sits in the queue and what upgrades the studies identified. Interconnection risk is often the biggest unpriced risk in renewable energy investments.

History & origin

Grid operators have long studied new generators before connection, but queues stayed manageable when most new plants were large and few. Cheap solar, wind, and batteries changed that in the 2010s, as thousands of smaller projects applied, many speculatively. Lawrence Berkeley National Laboratory's annual 'Queued Up' reports documented the backlog: about 2,290 gigawatts were waiting in US queues at the end of 2024, and roughly 2,060 gigawatts at the end of 2025, a 10% drop driven mostly by withdrawals. Only about 13% of capacity that applied between 2000 and 2020 had reached operation by the end of 2025. FERC's Order 2023, issued that July, required grouped 'cluster' studies and stricter readiness rules. In my view, the queue is where climate targets meet the physical limits of transmission lines.